# £42m Leigh flood storage upgrade completed to protect Tonbridge and Hildenborough

> The Environment Agency has completed a £42m expansion of the Leigh flood storage area and a new Hildenborough embankment, cutting flood risk to 1,870 homes and 575 businesses on the River Medway.

Published 16 November 2026 by The Water Wire. Topic: Investment & infrastructure. Canonical: https://waterwire.co.uk/story/leigh-flood-storage-hildenborough-scheme-completed

The Environment Agency's £42m upgrade of the Leigh flood storage area on the River Medway, together with a new embankment at Hildenborough, has officially opened. The [Environment Agency](https://www.gov.uk/government/news/new-flood-scheme-opens-to-protect-tonbridge-and-hildenborough) announced the opening on 30 September, and [Kent Online](https://www.kentonline.co.uk/tonbridge/news/work-on-42m-flood-defences-to-protect-1-870-kent-homes-comp-345703/) dated it to the previous day. The EA says the scheme reduces flood risk to 1,870 homes and 575 businesses. It adds that communities further downstream also benefit.

## What we know

According to the [Environment Agency](https://www.gov.uk/government/news/new-flood-scheme-opens-to-protect-tonbridge-and-hildenborough), the maximum stored water level at the control structure has been raised by 55cm. That increases capacity by about 23%, to roughly 7.4 million cubic metres. The work took three years, and the storage area stayed operational throughout.

Three new 12.5-tonne steel gates were fitted, along with new lifting and electrical systems, moving maintenance platforms and an eel pass. At Hildenborough, a 98m embankment, a new pumping station on the Hawden Stream and a sheet-piled wall now stop the Medway backing up into the village. The EA says about 180 homes there that flooded in 2013 benefit directly.

The EA puts the cost at about £42m and says the scheme will deliver more than £155m of benefits. Funding came from:

- £36.6m in Flood Defence Grant in Aid
- £2.5m from Kent County Council
- £2.3m from the South East Local Enterprise Partnership
- £500,000 from Tonbridge and Malling Borough Council
- £85,000 in levy funding

The agency says the work improves the structure's reliability and resilience, so it can keep reducing flood risk for the next 50 years. It also cautions that defences cannot eliminate flood risk entirely.

## What others are reporting

[Kent Online](https://www.kentonline.co.uk/tonbridge/news/work-on-42m-flood-defences-to-protect-1-870-kent-homes-comp-345703/) described the more than £23m of community benefits as an aim of the scheme. [New Civil Engineer](https://www.newcivilengineer.com/latest/42m-upgraded-flood-defences-completed-in-kent-02-10-2026/) repeated the EA's engineering and funding figures. [Water Magazine](https://www.watermagazine.co.uk/2026/11/16/new-flood-scheme-opens-to-protect-tonbridge-and-hildenborough/) has now carried the EA's figures on homes and businesses protected.

## Background

The original storage area, a 1.3km earth embankment between Leigh and Penshurst, was completed in 1982. The EA says it was operated 75 times between 1981 and summer 2026.

The expansion needed Secretary of State approval to raise the legal maximum stored level, and a public inquiry was held in 2021. In its [2021 release](https://www.gov.uk/government/news/leigh-flood-storage-area-expansion-scheme), the EA said it expected work to start in summer 2022 and finish in autumn 2024. At that time it expected the scheme to better protect over 1,400 homes and businesses.

In February 2024, [Kent Online](https://www.kentonline.co.uk/kent/news/21m-flood-storage-tank-upgrade-to-finally-begin-301216/) reported a cost of £21.2m and a 25% capacity increase. It said planning permission had been granted in November 2022.

## What to watch

- Whether the EA explains the rise from the £21.2m figure reported in 2024 to about £42m, and the slip from the 2024 completion date.
- How the enlarged storage area performs in its first winter of operation.
- Delivery of the stated social value commitments.

This is Environment Agency flood-defence capital spending, funded overwhelmingly by Defra's Flood Defence Grant in Aid. It is not water company or Ofwat-regulated investment, but it sits in the same catchment-resilience picture that utilities, councils and the EA all share.

The headline numbers are solid. Capacity is up about 23%, protection now covers 1,870 homes and 575 businesses, and the EA claims a benefit-cost ratio well above three to one.

The unresolved question is delivery. In 2021 the EA expected completion in autumn 2024. Regional press reported a cost of £21.2m in early 2024, and the outturn is about £42m. No source we have seen explains the gap. The 2024 figure came from press reporting rather than an EA document, so like-for-like comparison is uncertain. Even so, cost and schedule growth on flood capital schemes matters at a time of competing demands on public infrastructure budgets. It deserves a clear public account from the agency.

## Sources

- [Environment Agency (GOV.UK) — New flood scheme opens to protect Tonbridge and Hildenborough](https://www.gov.uk/government/news/new-flood-scheme-opens-to-protect-tonbridge-and-hildenborough)
- [Kent Online — Work on £42m flood defences completed](https://www.kentonline.co.uk/tonbridge/news/work-on-42m-flood-defences-to-protect-1-870-kent-homes-comp-345703/)
- [New Civil Engineer — £42m upgraded flood defences completed in Kent](https://www.newcivilengineer.com/latest/42m-upgraded-flood-defences-completed-in-kent-02-10-2026/)
- [Water Magazine — New flood scheme opens to protect Tonbridge and Hildenborough](https://www.watermagazine.co.uk/2026/11/16/new-flood-scheme-opens-to-protect-tonbridge-and-hildenborough/)
- [Environment Agency (GOV.UK) — Leigh flood storage area expansion scheme](https://www.gov.uk/government/news/leigh-flood-storage-area-expansion-scheme)
- [Kent Online — £21m flood storage upgrade to finally begin](https://www.kentonline.co.uk/kent/news/21m-flood-storage-tank-upgrade-to-finally-begin-301216/)