# Ofwat decision on market code change for disputed payment withholdings is overdue

> MOSL says Ofwat has missed the planned timescale for deciding on CPM054 and CPW145, the change on withheld charges in disputes, so the planned implementation date can no longer be met.

Published 12 November 2026 by The Water Wire. Topic: Regulation & policy. Canonical: https://waterwire.co.uk/story/ofwat-decision-mosl-dispute-withholdings-change-overdue

Ofwat has missed the planned timescale for deciding on a business retail market code change on deductions and withholdings under the dispute process, according to market operator MOSL. As a result, the planned implementation date can no longer be met. The change, CPM054 and CPW145, appears on a slide headed "Awaiting Ofwat Decision" in the [MOSL](https://mosl.co.uk/documents-publications/11522-virtual-user-forum-slide-deck-nov-2026/file) slide deck for its November virtual user forum. The slide reflects the position as at 4 November 2026.

## What we know

- MOSL's slide footnote says the planned timescale for Ofwat's decision has passed and the planned implementation date is no longer achievable.
- If Ofwat later approves the change, Ofwat and MOSL will agree a new implementation date.
- The Code Change Committee (CCC) recommended the change by "Majority Rejection".
- The decision-due and implementation-date fields on the slide are masked, and the change is listed as having no system impact.

The same slide lists four other changes awaiting an Ofwat decision. The CCC recommended all of them unanimously:

- CPM061 and CPW158, on data and report requests of the market operator.
- CPW159, on estimated transfer reads.
- CPM063 and CPW153, the Interim Supply cost recovery mechanism.
- CPW154, Interim Supply initial cost support.

Ofwat has consulted on "minded to" decisions for the two Interim Supply changes. The slide does not say whether those decisions are also late.

The Water Wire found no statement from Ofwat on when it will decide on CPM054 and CPW145.

## Background

According to [MOSL](https://mosl.co.uk/change/changes/deductions-and-withholdings-under-formal-disputes-process), the change aims to give visibility of, and standardise, how full or partial withholdings of primary charges are resolved. Section 9.7.2 of the Business Terms permits such withholdings. The change proposes making withheld amounts subject to the formal disputes process.

The proposal was first raised in July 2023, before MOSL's December 2023 improvements to the change process. MOSL's documents timeline shows prioritisation in August and October 2024 and a consultation pack in November 2024. On 13 May 2025 the CCC agreed the original proposer could withdraw the change unless another party adopted it. A version 2.0 proposal form followed on 3 June 2025 and a change plan on 8 July 2025.

Minutes of the CCC's 41st open session, published by [MOSL](https://mosl.co.uk/document/groups-and-committees/code-change-committee/9917-ccc41-open-session-minutes-v1-2/file), record two points:

- Thames Water adopted the change as CPM054.R1 and CPW145.R1, and a revised plan was tabled.
- Members raised concerns about delivering updates in August 2025 because of the data team's workload.

Ofwat has the power to approve or reject code modifications. The panel that makes recommendations includes wholesaler and retailer members and three independent members appointed by MOSL.

## What to watch

- Ofwat's decision on CPM054 and CPW145, and whether it follows the CCC's majority recommendation to reject.
- A new implementation date, to be agreed by Ofwat and MOSL if the change is approved.
- Ofwat's final decisions on the Interim Supply changes, CPM063, CPW153 and CPW154, after its "minded to" consultations.

This change has been in the system for more than three years. It was raised in July 2023, nearly withdrawn in May 2025 and then adopted by Thames Water. Ofwat's decision is now past its planned timescale.

The substance matters to trading parties. How withheld primary charges are handled affects wholesale-retail cash flow and how commercial disputes are settled.

The unusual feature is the recommendation itself. The CCC recommended rejection by majority, whereas every other item on the waiting list was recommended unanimously. That may make Ofwat's call harder, but neither MOSL nor Ofwat has published a reason for the delay.

Whatever Ofwat decides will show how far it defers to a divided industry panel on a change with no system impact but commercial consequences. Until then, the market has no date to plan around.

The backlog of five changes awaiting a decision is also worth watching as the code change process tries to move faster.

## Sources

- [MOSL — Virtual user forum slide deck, November 2026](https://mosl.co.uk/documents-publications/11522-virtual-user-forum-slide-deck-nov-2026/file)
- [MOSL — Deductions and withholdings under formal disputes process](https://mosl.co.uk/change/changes/deductions-and-withholdings-under-formal-disputes-process)
- [MOSL — CCC41 open session minutes](https://mosl.co.uk/document/groups-and-committees/code-change-committee/9917-ccc41-open-session-minutes-v1-2/file)