# Storm overflows: Kier starts £7.9m Pudsey scheme for Yorkshire Water as UU finishes Kirkham tunnel early

> Yorkshire Water's first scheme to reach construction under Kier's AMP8 framework will add 2,500m³ of storage in Pudsey, while United Utilities has completed a £5.5m storm water tunnel in Kirkham ahead of schedule.

Published 9 November 2026 by The Water Wire. Topic: Investment & infrastructure. Canonical: https://waterwire.co.uk/story/storm-overflow-schemes-pudsey-kirkham

Two storm overflow schemes have reached milestones: one is moving into construction and one is finished.

## What we know

**Pudsey, Yorkshire Water.** Kier will deliver a £7.9m scheme at Kent Road in Pudsey, the first to move into main construction under its AMP8 Complex Non-Infrastructure Framework with Yorkshire Water ([Water Magazine](https://www.watermagazine.co.uk/2026/11/09/kier-appointed-to-deliver-7-9m-pudsey-storm-overflow-scheme-for-yorkshire-water/)).
- With design partner SWECO, Kier will build about 2,500m³ of offline storage on the pipeline from the Kent Road combined sewer overflow, holding flows in heavy rain and returning them for treatment later.
- The aim is to improve discharge performance into a tributary of Pudsey/Farnley Beck and reduce unionised ammonia entering the watercourse.
- The work includes a storage shaft, chambers, pipework, pumping and mixing equipment, and electrical and control systems.

**Kirkham, United Utilities.** A £5.5m stormwater tunnel in Kirkham, Lancashire, has been completed ahead of schedule ([Water Magazine](https://www.watermagazine.co.uk/2026/11/09/kirkhams-5-5m-storm-overflow-project-completed-early/)).
- The 300m tunnel, four metres below ground, stores more than two million litres of stormwater.
- It is designed to cut how often storm overflows operate into Wrangway Brook, a tributary of the River Ribble, and to ease peak flows to Freckleton pumping station and Clifton Marsh treatment works.
- United Utilities says it is investing more than £13bn in the North West, including work to protect and enhance over 500km of rivers, lakes and bathing waters.

> **2,500m³** — offline storm storage to be built at Kent Road, Pudsey ([source](https://www.watermagazine.co.uk/2026/11/09/kier-appointed-to-deliver-7-9m-pudsey-storm-overflow-scheme-for-yorkshire-water/))

## Background

Both schemes support the Environment Act 2021 duty to progressively reduce the harm from storm overflow discharges and the government's [Storm Overflows Discharge Reduction Plan](https://www.gov.uk/government/publications/storm-overflows-discharge-reduction-plan). Both companies are under scrutiny on wastewater performance: Yorkshire Water received a one-star rating in the Environment Agency's latest environmental performance assessment ([our story](/story/yorkshire-water-one-star-response-and-new-ceo)).

## What to watch

- Whether Kier's framework moves further schemes into construction this year, as Yorkshire Water ramps up AMP8 delivery.
- Spill data for the Kirkham overflows over the coming winter, the real test of the tunnel.

Individually these are modest schemes. Together they show what AMP8 overflow delivery looks like in practice: many local storage projects, each cutting spills at one or two outfalls. The sector's credibility depends on getting hundreds of these built on time, and on spill data then showing a difference.

Finishing early is worth noting at a time when regulators are watching for slippage. For Yorkshire Water, getting the first framework scheme into construction is a start, but after a one-star rating, the pace of what follows will matter more.

## Sources

- [Water Magazine — Kier appointed to deliver £7.9m Pudsey storm overflow scheme for Yorkshire Water](https://www.watermagazine.co.uk/2026/11/09/kier-appointed-to-deliver-7-9m-pudsey-storm-overflow-scheme-for-yorkshire-water/)
- [Water Magazine — Kirkham's £5.5m storm overflow project completed early](https://www.watermagazine.co.uk/2026/11/09/kirkhams-5-5m-storm-overflow-project-completed-early/)
- [Defra — Storm Overflows Discharge Reduction Plan](https://www.gov.uk/government/publications/storm-overflows-discharge-reduction-plan)