Anglian Water has started a £30m upgrade at Boston, Lincolnshire, adding a 4.5 million litre storm tank and an extra pump to reduce overflows in heavy rain. UV treatment is planned for 2028.
By The Water Wire · Edited by David Bain

Anglian Water has started work on a £30m project to reduce sewage spills in Boston, Lincolnshire. The scheme adds storm storage and pumping capacity at the town's wastewater sites, with a UV treatment stage to follow in 2028, BBC News reported. The figures below come from that report. The Water Wire could not access Anglian Water's own announcement to check them.
What we know
- Anglian Water said it is upgrading its sewage treatment works in Boston with a new storm tank that holds 4.5 million litres, according to the BBC.
- An extra pump is being installed at East Side Pumping Station to reduce wastewater overflows in heavy rain.
- Project manager Brian Drayton said wastewater from across the area passes through East Side Pumping Station before it is treated at Boston Water Recycling Centre.
- In heavy rain, the extra pump will let more wastewater reach the treatment works. The storm tank will hold some of the flow until it can be treated.
- Drayton told the BBC: "It's all aimed at reducing spills into the environment."
- The site is off Scalp Road. Work is expected to finish in spring 2027.
- The company plans to install an ultraviolet (UV) treatment system at the site in 2028 to reduce bacteria in treated wastewater. Drayton said this would improve water quality without additional chemicals. He added that "the River Haven and the Wash will be much cleaner as well".
Background
The BBC said Anglian Water recently announced £350m of investment across Lincolnshire between 2025 and 2030. That programme covers water supply, the environment and growing communities.
The design follows a common approach to storm overflows. Raising forward pumping capacity sends more flow to treatment during wet weather. Storage then holds back the excess flow instead of spilling it.
We could not establish several points:
- Boston-specific spill data from Event Duration Monitoring.
- How the £30m figure is broken down.
- How the scheme is funded under the current price control.
We found no independent reaction to the scheme.
What to watch
- Whether Anglian Water's own release confirms the £30m figure and the scope of the scheme.
- Whether the storm tank and extra pump are delivered by the spring 2027 target.
- Event Duration Monitoring returns for the Boston sites once the new capacity is in use.
- Progress on the UV treatment system planned for 2028, and its effect on bacteria levels downstream in the River Haven and the Wash.
- How the scheme fits within the wider £350m Lincolnshire programme for 2025 to 2030.
Sources
Summarised in our own words. Spotted an error? Tell us — we correct visibly.
Read next
More investment →
InvestmentDefra launches £43m for farm reservoirs, water storage and farming innovation
Defra is offering up to £15m in grants for on-farm water storage and £28m for farming innovation after a dry summer. The CLA called it a welcome first step but wants a longer-term commitment.
InvestmentICE and Future Governance Forum call for citizens' input into national infrastructure strategy
A joint report, A Mandate to Build, says giving communities and local leaders a meaningful voice could speed up infrastructure delivery and cut costs. That matters for any sector planning major schemes.
InvestmentUKWIR seeks partners to rebuild the National Failures Database for pipes and sewers
Up to £400,000 is on offer to replace the 20-year-old database of water and sewer pipe failures with a cloud platform, ready to inform business plans in autumn 2028.
The Current · Free
The UK water industry in two minutes, every weekday.
Sourced, independent, no spin. Unsubscribe any time. Privacy notice.