Thames Water submits White Horse Reservoir plans to the Planning Inspectorate

Thames Water has applied for a Development Consent Order for the reservoir near Abingdon, formerly known as SESRO. The Planning Inspectorate now has up to 28 days to decide whether to accept it for examination.

By The Water Wire · Edited by David Bain

Abstract illustration: a long cyan timeline line receding into the distance with infrastructure blocks growing along it.
Illustration: AI-generated for The Water Wire
Original sourceThames Water — White Horse Reservoir in Oxfordshirethameswater.co.ukRead ↗

Thames Water has submitted its Development Consent Order (DCO) application for White Horse Reservoir to the Planning Inspectorate (PINS). The scheme in Oxfordshire was previously known as the South East Strategic Reservoir Option (SESRO). The company said it filed the application on 19 November 2026 and described it as the first step in the planning application process.

What we know

  • Acceptance decision. PINS will decide whether to accept the application for examination. Thames Water says this review can take up to 28 days.
  • Public participation. If the application is accepted, the documents will be published on the PINS website. Anyone can then register as an interested party and take part in the examination, according to Thames Water.
  • How it would work. The reservoir would be filled with water from the River Thames in winter. Water would be released when river levels fall or demand rises.
  • Who it would serve. The project website says the reservoir would help supply around 15 million people across the South East.
  • Other features. The project website also sets out recreation, wetland and nature features, shown in illustrative images.

What others are reporting

Infrastructure Now reported the submission on 19 November. Its headline puts the cost of the reservoir at £7bn. Its summary describes a proposed 150bn-litre reservoir south-west of Abingdon and notes that new images have been released alongside the application.

Background

The scheme has been taken through the gated process run by RAPID, the Regulators' Alliance for Progressing Infrastructure Development. Thames Water's reservoir page links to the reports for Gates 1, 2 and 3. The Gate 3 documents are filed under the SESRO name and include material responding to RAPID queries on:

  • cost estimates
  • whole-life costs
  • embankment slopes
  • stranded assets

The project website lists earlier engagement, including a SESRO public consultation in 2024 that has now closed.

What to watch

  • Whether PINS accepts the application for examination within the review period of up to 28 days.
  • Publication of the application documents on the PINS website, and the opening of registration for interested parties.
  • Reaction from local councils, campaigners and regulators as the examination approaches.
  • How the published cost figures compare with the estimates scrutinised during the RAPID gate process.

Sources

  1. 1Thames Water — White Horse Reservoir in Oxfordshire thameswater.co.uk ↗
  2. 2Thames Water SRO — White Horse Reservoir project page thames-sro.co.uk ↗
  3. 3Thames Water SRO — Strategic resource options home page thames-sro.co.uk ↗
  4. 4Infrastructure Now — Thames Water submits DCO for £7bn reservoir near Abingdon infrastructure-now.co.uk ↗
  5. 5watermagazine.co.uk watermagazine.co.uk ↗

Summarised in our own words. Spotted an error? Tell us — we correct visibly.

The Current · Free

The UK water industry in two minutes, every weekday.

Sourced, independent, no spin. Unsubscribe any time. Privacy notice.